Demolition of the old lab is now complete ready for us to start construction on the packing plant extension. The works included demolishing an existing building, breaking up a series of road slabs, removing all the foundations and then crushing the material to be reused on site. We produced around 1500t of crushed material, which was used as backfill around the main structure. (Before and after pictures attached).

BeforeAfter