Project was the construction of two Vestas V90 2MV Gridstreamers.

Works included:

  • Temporary road, haul roads, improvement to highway.
  • Crane hardstandings and turbine foundations
  • On-site cabling, trenching and ELNW Ducting
  • Anemometer mast and foundation, construction of substation and control building.