Island Bridge
Works included dismantling and removing of existing bridge structure, lifting off the bridge beams, breaking down the abutments and replacing with RC abutments pads with new abutments installed.
Stonework to central pier and the two new end abutments.
A new Omnia Deck installed using crane and harnesses.
Works to carriage-way above the bridge deck included surface course, binder, road base and waterproofing layer.
Finally, tie into existing carriage-way, re-instate existing railings and soil.
Job name: Summerseats Bridge, Client: Cruden Value: £435,000.00